Past Performances
Prime Controls has been involved in automation, electrical distribution and water treatment projects since 1991.
Design, supply and installation of a 1.5MW, 4160V generator, ATS and primary line feeder. Work includes civil and electrical design and construction.
Provide a new electrical feeder and MCC for the six new Influent Pumps at the Influent Pump Station electrical room, consisting of two sets of 3 # 750MCM & 1#4/0 RHH conductor from switchgear to new power panel for 1200’
Supply and installation of 1250KW generator and transfer switch at effluent pumps station.
Metropolitan Detention Center Guaynabo, Control Center Upgrade for all facility including CCTV, UPS and Programable Logic Controllers for security. Work done on line.
Water Filtration Plant North and Metro Region, including supply and installation of Turbidity, PH, and Chlorine Analyzers, Flow, Pressure and Level Meters, Chlorine Control Valves and dossing equipment’s, Control Panels and RIO, Wonderware Work Station, Transformers, Distribution Panels and CCTV for (6) Water Filter plants.
Project consist of (2) Main Pump Station, complete electrical work including: supply and install 500KVA substation, 300KW generator, 150KVA Substation, 125KW generator, Motor Control Center, Control Panels and Lighting.
Provide and install in existing MCC, (4) 350HP Variable Frequency Drives, control logic, instruments and installation of mechanical equipment in main lift station line.
Supply and installation of a Central Control and Automation System including Radio Control, Scada Workstations and Motor Control Centers and Control Panels at Carolina Regional Waste Water Treatment Plant.
Rehabilitation and complete electrical work including new Motor Control Centers for Filter Plant and Raw Water, Control Panels, Radio Control, Instrumentation, ATS and Generator, Power and Distribution. Work done with plant running.
Rehabilitation of various Puerto Rico Aqueducts and Sewer Authority (AAA) Waste Water Treatment Plant (WWTP), Water Filtration Plants (WTP) and Pump Stations as part of the emergency Recovery Contractors after the Hurricane Maria.
Complete plant rehabilitation including mechanical, electrical and civil work.